CEDEX test track

IMAGEN 591  2

 

LIFESURE project action B, implementation actions, includes manufacture and laying of half-warm bituminous recycling asphalt at CEDEX test track. This task targets at sudying those structural variables that are highly complex to be assessed in in-service roads. The principal objective is characterisation of the pavement performance changes due to load application and environmental conditions.

Three different stretches of road had been constructed: conventional hot mix asphalt AC16S bin 35/50 S, half-warm mix recycling asphalt at total recycling rate (100% RAP), half-warm mix recycling asphalt 70% recycling rate (70% RAP).

Charateristic of test track sections:

- Length: 25 m, three sections of 7 m with different surface layer.

- Width: 3 m.

- Layer thickness: 5 cm.

.

 

.secc ens b.

 

Accelerated test and monitoring of CEDEX test track are expected last one year. Structural performance of the sections will be periodically evaluated throughout the test in terms of bearing capacity, surface cracking and rutting. Embedded sensors will be located for daily monitoring and the noise perceived in each section will be also tested.

 

.planinstrum b  

 

Construction of CEDEX test track sections 

 

Lifesure in twitter

Latest

Final Workshop of the LIFSURE project

05 October 2018

On October 17, 2018 at 4:30 p.m., the final workshop of the LIFESURE project will be held during the course of the National Signing Symposium that will take place in Madrid on October 16, 17 and 18. Simposio Nacional de Firmes

LIFESURE project present at the XV Road Conservation Conference

28 May 2018

LIFESURE project present at the XV Road Conservation Conference held in Valencia on 22, 23 and 24 May 2018. Presente y Futuro de la Conservación de Carreteras y la Preservación del Patrimonio.

LIFESURE project in the Circular Economy workshop Acciona Construcción

04 December 2017

LIFESURE project in the workshop "Promoting circular economy for a greener road construction" held on 22 November 2017 organized by Acciona Construction. Program (http://media.acciona-construccion.com/media/14998409/draft-programme_wokshop_221117.pdf) Photos (index.php?option=com_content view=article id=331:fotos-jornada-ecocir-acciona-ingles catid=31:noticias-2)

Private area

  • Prueba de mapa de imágenes sacyr uhu uhu

      Sitemap   

              Count:
    846895